Get the Progress Report HERE: Today's Progress Report

​

INSTA-stats:

1.  Repair Laundry Floor and Tile Laundry (VCT). Install Wall Base: COMPLETED

2.  "Standard" Guest Room Tile Demo and Re-Tile (45 Rooms) : COMPLETED     

3.  Breakfast Area/Main Lobby/Suite Shop/Vestibule/Corridors E&W/Ante Room/Rest Room Approach/Elevator Approach DEMO

     COMPLETED

4.  Breakfast Area/Main Lobby/Suite Shop/Vestibule/Corridors E&W/Ante Room/Rest Room Approach/Elevator Approach TILING

     COMPLETED

5.   Main Lobby/Community Area Carpeting (w/pad): COMPLETED

6.   Bathtub Refinishing (3 bathtubs): COMPLETED

7.   Shower/Tub Caulking (69 Rooms): COMPLETED

8.   Fabrication and Installation of Coffee Service/Media CenterCOMPLETED

9.   Fabrication and Installation of Suite Shop Displayer Unit 1COMPLETED

10. Fabrication and Installation of Suite Shop Displayer Unit2COMPLETED

11. Fabrication and Installation of Suite Shop Quartz CountertopsCOMPLETED

12. Fabrication and Installation of Guest Laundry Quartz Countertops: COMPLETED

START DATE: MARCH 10

REPORT DATE: MARCH 31

13. Installation of Tile in Floor and Walls of Women's Public RestroomsCOMPLETED

14. Installation of Tile in Floor and Walls of Men's Public RestroomCOMPLETED

15. Removal/Hauling of Guest Room Furnishings in Rooms 101-130 and 201-127: COMPLETED

16. Reception (Offloading and Portage) & STORAGE OF CARPET, Guest Rooms: COMPLETED

17. Reception (Offloading and Portage) & STORAGE OF CARPET, Corridors, Lobby & Public Space: COMPLETED

18. Reception (Offloading and Portage) & STORAGE OF MIRRORS (140 units ): COMPLETED 

19. Reception (Offloading and Portage) & STORAGE OF TELEVISIONS (70 units): COMPLETED

20. Reception (Offloading and Portage) & STORAGE OF ARTWORK (210 units): COMPLETED

21. Reception (Offloading and Portage) & STORAGE OF HOTEL LIGHTING (332 units): COMPLETED

22. Demo of Guest Suite Room TILES: 12 Rooms (Floors 1 & 2) 4 Rooms Remaining for Demo 

23. Demo of Guest Suite Room WET BARS: 12 Rooms (Floors 1 & 2); 4 Rooms Remaining for Demo

24. Carpet Demo/Removal from Guest Rooms: 27 Rooms  (Rooms 101-226)

25. Carpeting & Base of Guest Rooms: 14 Rooms (1st Floor)

26. Repair of Sheetrock in Lobby and Public Restrooms (Sheetrock, taping, blending, texture): COMPLETED

27. Installation of Closet Packages [Fulfilling Contract for 70] (6)

28. Reception (Offloading and Portage) & STORAGE OF HOTEL SEATING (Couches, Lounge Chairs and Desk Chairs): COMPLETED

29. Carpeting & Base of Guest Rooms: 18 Rooms (2nd Floor) COMPLETED

30. Demo of Guest Suite Room TILES: 4 Rooms (2nd Floor) COMPLETED

31. Reception (Offloading and Portage) & STORAGE OF FURNISHINGS (2 Trucks/6 hours: All Streamlined Desks, Panels, Headboards,

C-Tables, Clothing Chests, TV Panels, Side Panels,Nightstands, Quartz Table Tops) : COMPLETED

​

​

​

​

​

​

​

 

Change Is Happening Fast.

Piece by piece, the puzzle is coming together. The new Media Center is installed and functioning. We've installed the newly redesigned Suite Shop Display Fixture and it's fully stocked!

The last of the Lobby Tile has been completed. WE'RE MOVING ON. 

Click here to view the Lobby Project Story

Hint: Scroll to the bottom and watch our TOUR Video while you're there.

​