Get the Progress Report HERE: Today's Progress Report
​
INSTA-stats:
1. Repair Laundry Floor and Tile Laundry (VCT). Install Wall Base: COMPLETED
2. "Standard" Guest Room Tile Demo and Re-Tile (45 Rooms) : COMPLETED
3. Breakfast Area/Main Lobby/Suite Shop/Vestibule/Corridors E&W/Ante Room/Rest Room Approach/Elevator Approach DEMO
COMPLETED
4. Breakfast Area/Main Lobby/Suite Shop/Vestibule/Corridors E&W/Ante Room/Rest Room Approach/Elevator Approach TILING
COMPLETED
5. Main Lobby/Community Area Carpeting (w/pad): COMPLETED
6. Bathtub Refinishing (3 bathtubs): COMPLETED
7. Shower/Tub Caulking (69 Rooms): COMPLETED
8. Fabrication and Installation of Coffee Service/Media Center: COMPLETED
9. Fabrication and Installation of Suite Shop Displayer Unit 1: COMPLETED
10. Fabrication and Installation of Suite Shop Displayer Unit2: COMPLETED
11. Fabrication and Installation of Suite Shop Quartz Countertops: COMPLETED
12. Fabrication and Installation of Guest Laundry Quartz Countertops: COMPLETED
START DATE: MARCH 10
REPORT DATE: MARCH 31
13. Installation of Tile in Floor and Walls of Women's Public Restrooms: COMPLETED
14. Installation of Tile in Floor and Walls of Men's Public Restroom: COMPLETED
15. Removal/Hauling of Guest Room Furnishings in Rooms 101-130 and 201-127: COMPLETED
16. Reception (Offloading and Portage) & STORAGE OF CARPET, Guest Rooms: COMPLETED
17. Reception (Offloading and Portage) & STORAGE OF CARPET, Corridors, Lobby & Public Space: COMPLETED
18. Reception (Offloading and Portage) & STORAGE OF MIRRORS (140 units ): COMPLETED
19. Reception (Offloading and Portage) & STORAGE OF TELEVISIONS (70 units): COMPLETED
20. Reception (Offloading and Portage) & STORAGE OF ARTWORK (210 units): COMPLETED
21. Reception (Offloading and Portage) & STORAGE OF HOTEL LIGHTING (332 units): COMPLETED
22. Demo of Guest Suite Room TILES: 12 Rooms (Floors 1 & 2) 4 Rooms Remaining for Demo
23. Demo of Guest Suite Room WET BARS: 12 Rooms (Floors 1 & 2); 4 Rooms Remaining for Demo
24. Carpet Demo/Removal from Guest Rooms: 27 Rooms (Rooms 101-226)
25. Carpeting & Base of Guest Rooms: 14 Rooms (1st Floor)
26. Repair of Sheetrock in Lobby and Public Restrooms (Sheetrock, taping, blending, texture): COMPLETED
27. Installation of Closet Packages [Fulfilling Contract for 70] (6)
28. Reception (Offloading and Portage) & STORAGE OF HOTEL SEATING (Couches, Lounge Chairs and Desk Chairs): COMPLETED
29. Carpeting & Base of Guest Rooms: 18 Rooms (2nd Floor) COMPLETED
30. Demo of Guest Suite Room TILES: 4 Rooms (2nd Floor) COMPLETED
31. Reception (Offloading and Portage) & STORAGE OF FURNISHINGS (2 Trucks/6 hours: All Streamlined Desks, Panels, Headboards,
C-Tables, Clothing Chests, TV Panels, Side Panels,Nightstands, Quartz Table Tops) : COMPLETED
​
​
​
​
​
​
Change Is Happening Fast.
Piece by piece, the puzzle is coming together. The new Media Center is installed and functioning. We've installed the newly redesigned Suite Shop Display Fixture and it's fully stocked!
The last of the Lobby Tile has been completed. WE'RE MOVING ON.
Click here to view the Lobby Project Story
Hint: Scroll to the bottom and watch our TOUR Video while you're there.
​